Update expansion barge terminal | Milestone achieved

We have taken another important step. The new site has been put into operation, and the work is progressing steadily.

The electrical infrastructure is currently being completed and our second crane will be delivered in Q2-2025, with plans to have it operational by the end of Q3-2025. In the meantime, the existing crane has recently been modified to allow it to move across the entire length of the quay. This provides the possibility for as many as 4 docking spots when we assume ships with a width of 4 containers that can dock side by side.

Another significant step forward and a valuable improvement to our capacity!